Offshore Mediterranean

Compressor Installation

In the first half of 2010, PES fabricated and installed several flowlines and a manifold for the Mari-B production facility. PES also installed three compressor modules totaling 1,600 tons and associated piping and equipment.

As a result of the successful execution of that project, PES was asked to support two critical projects for the Operator  in the country 1) a subsea tie-back from the Noa field to the Mari-B production unit and 2) hook-up of the Tamar platform.

These two projects are unique for PES because of both the scale and scope of work. PES deployed over  180 individuals working offshore on both the platforms. This represents one of the largest single projects the company has executed.